Hyperscale Data Center — 25% WUE Improvement
CASE STUDY · HYPERSCALE DATA CENTER · ESG / WUE

Hyperscale data center improves WUE by 25% and saves 136.8M gallons per year — with Tier 3 / Tier 4 availability intact

Water Saved: 136.8M gal / yr
25%
WUE improvement
136.8M gallons / yr
Water saved
$150,000 / yr
Chem + sewer cost
Unblocked
Expansion

What this case study covers

A hyperscale data center operator was blocked from expanding into preferred locations by water demand. High-calcium makeup water and a phosphate-based program held the system to only 3 cycles of concentration.

Inside this case study

← Back to Data Center Case Study
📄

Download the Full Case Study

Free · PDF · No spam

Your download is ready

Thank you. Click the button below to download the full case study PDF.

Download PDF

Jim may also be in touch — feel free to reply directly with any questions.

🔒 No spam · Independent advisory · No chemistry sold

Independent · Vendor-Neutral

Have a similar challenge at your facility?

Most assessments begin with a remote review. No vendor pitch — just engineering.

Schedule a Discovery Call